Common estimation methods
1. SWAG (Scientific Wild-Ass Guess)
- Description: A rough, experience-based guess that lacks detailed analysis.
- When to Use:
- Early-stage discussions when little information is available.
- When a quick ballpark figure is needed.
- Informal or exploratory planning.
- Example:
"This project might take around six months, but we need more details to be sure."
2. ROM (Rough Order of Magnitude)
- Description: A high-level estimate with a broad accuracy range (typically ±50% or more).
- When to Use:
- Initial feasibility studies.
- Budgeting and executive decision-making.
- Before detailed scope or requirements are available.
- Example:
"This project will cost between $500K and $1M."
3. T-Shirt Sizing (XS, S, M, L, XL, XXL, etc.)
- Description: Uses broad size categories instead of precise numbers, often based on complexity or effort.
- When to Use:
- Agile development and backlog grooming.
- When detailed effort estimation isn't practical.
- Relative comparisons between tasks rather than absolute time estimates.
- Example:
"Feature A is a Medium, but Feature B is an XL, so it will take significantly longer."
4. Three-Point Estimation (PERT: Program Evaluation and Review Technique)
- Description: Uses three estimates—Optimistic (O), Pessimistic (P), and Most Likely (M)—to calculate an expected value using the formula:
[ E = \frac{O + 4M + P}{6} ] - When to Use:
- When uncertainty needs to be factored into planning.
- For more accurate and risk-aware estimates.
- Example:
"Best case: 3 days, worst case: 10 days, most likely: 6 days. Expected time = (3 + 4×6 + 10) ÷ 6 ≈ 6.2 days."
5. Story Points (Agile Estimation)
- Description: Assigns effort values to user stories based on complexity, risk, and unknowns, often using Fibonacci-like sequences (1, 2, 3, 5, 8, etc.).
- When to Use:
- Agile teams working with Scrum or Kanban.
- When estimating development effort without tying it directly to time.
- Example:
"This user story is a 5 because it's more complex than a 3 but not as large as an 8."
Choosing the Right Estimation Method
Method | Accuracy | Best Used For |
---|---|---|
SWAG | Very Low | Quick ballpark figures, informal discussions |
ROM | Low | Early feasibility, budget planning |
T-Shirt Sizing | Medium | Agile backlog sizing, high-level estimates |
Three-Point (PERT) | High | Risk-aware estimation, detailed planning |
Story Points | Medium-High | Agile development, effort-based planning |
Share on X (Twitter) Share on LinkedIn Share on Facebook